DVC Power Stations at a Glance
Station
Location
Unit
Installed Capacity
Commissioned
Chandrapura TPS
(CTPS)
 
Dist. Bokaro
1
130 MW
Oct. 1964
Jharkhand
2
130 MW
May 1965
3
130 MW
Jul. 1968
Chandrapura PH#II
(CTPS)
 
Dist. Bokaro
Jharkhand
1
250 MW
Nov. 2011
2
250 MW
Jul. 2011
Durgapur TPS
(DTPS)
Dist. Burdwan
3
140 MW
Dec.1966
West Bengal
4
210 MW
Sep. 1982
Bokaro B TPS
(BTPS B)
 
Dist. Bokaro
1
210 MW
Mar. 1986
Jharkhand
2
210 MW
Nov. 1990
3
210 MW
Aug. 1993
Mejia TPS
(MTPS)
 
Dist. Bankura
1
210 MW
Mar. 1996
West Bengal
2
210 MW
Mar. 1998
3
210 MW
Sep. 1999
4
210 MW
Feb. 2005
5
250 MW
Feb. 2008
6
250 MW
Sept . 2008
Mejia PH#II
(MTPS)
 
Dist. Bankura
West Bengal
1
500 MW
Aug. 2011
Total Thermal
3710 MW
Tilaiya Hydel
(THS)
Dist. Hazaribagh
1
2 MW
Feb. 1953
Jharkhand
2
2 MW
Jul. 1953
Maithon Hydel
(MHS)
Dist. Burdwan
1
20 MW
Oct. 1957
West Bengal
2
20 MW
Mar. 1958
3
20 MW
Dec. 1958
Panchet Hydel
(PHS)
Dist. Dhanbad
1
40 MW
Dec. 1959
Jharkhand
2
40 MW
Mar. 1991
Total Hydel
144 MW
GROSS TOTAL
3854 MW

11th Plan Capacity Addition Programme

Sl. No.

Project

Unit

Capacity
(MW)

Commissiong

Project implementation by DVC own
1

MTPS Extension

Unit#5

250 MW

29.02.2008

2

MTPS Extension

Unit#6

250 MW

24.09.2008

3

CTPS Extension

Unit#7

250 MW

04.11.2009

4

CTPS Extension

Unit#8

250 MW

03/2009

5

MTPS Phase-II TPS

Unit#1

500 MW

04/2010

6

MTPS Phase-II TPS

Unit#2

500 MW

06/2010

7

Koderma TPS

Unit#1

500 MW

09/2010

8

Koderma TPS

Unit#2

500 MW

03/2011

9

Durgapur Steel TPS

Unit#1

500 MW

09/2010

10

Durgapur Steel TPS

Unit#2

500 MW

03/2011

11

Raghunathpur Ph-I TPS

Unit#1

600 MW

09/2011

12

Raghunathpur Ph-I TPS

Unit#2

600 MW

11/2011

Project implementation through Joint Venture
1

Maithon RB TPS [by MPL, JV of DVC & TPC]

Unit#1

500 MW 08/2010

Unit#2

500 MW 02/2011